Good morning Vietnam!!
I thought there was going to be some type of investor event on March 1, 2023.I hope to hear something on the investor day in May. COME ON TESLA!
I don't see the connection, yes the two foundations mean two 9k ton presses as expected but what makes you think the second one has already arrived?@Throwcomputer beat me to it, but you can very clearly see the second base sitting in the background. There will be 2 presses in this area and it looks like the 2nd one is also a 9k Ton Press.
This is starting to look more and more like they sneaked 2 presses in and are going to build them in parallel.
![]()
They poured 2 foundations for presses. You can see the orange forklift in the middle of the second foundation. They usually don’t pour the foundation for these until a few weeks prior to installation. That’s why there were giant holes in the floor here 6 weeks ago.I’m not seeing a second press? I’m regarded and all, but…. Help the greggertruck out
Okay, fine.They poured 2 foundations for presses. You can see the orange forklift in the middle of the second foundation. They usually don’t pour the foundation for these until a few weeks prior to installation. That’s why there were giant holes in the floor here 6 weeks ago.
With the number of parts they’ve received, I think there is a fair chance they’ve actually received 2 full presses and will be installing them one after the other (and partially in parallel). Either both for the Cybertruck, or 1 for the Cybertruck and one for the next gen vehicle.
Wanna see my Bean(is)?Here you go, this profile picture has my Model Y in it.
I do not even see all the parts needed for a single press, so you must be sniffing something great to see any parts for a second press. They have the 2 stationary platens and the moving platen. They have the 4 lg shafts (in crates) and at least 3 of the hinge pieces. I think they need more (maybe 6?) and they may be hiding somewhere. Then they need about 12 small shafts to mount the hinges to the stationary platens and the moving platen and we only 'see' 1 in the pic though we know there are at least 2 in here somewhere. All the rest is for the foundry. No second unit. That said it 'is' clear that they have a location for a second press.@Throwcomputer beat me to it, but you can very clearly see the second base sitting in the background. There will be 2 presses in this area and it looks like the 2nd one is also a 9k Ton Press.
This is starting to look more and more like they sneaked 2 presses in and are going to build them in parallel.
![]()
9-10 months. It depends on what you consider production. They started receiving gigapress parts in mid January and the the first Model Ys were being built before the end of the year. We saw them driving around in that timeframe.How long did it take from installation of Giga Press to first production for model Y? Less than a year right?