Below is a a weekly estimate based on time they've had for parts creation, experience from other production lines, etc. So 40,000 is viable, but highly optimistic. 25K would be more likely.40K between ~Sept 30 and Dec 31 2023????
that seems … optimistic
would likely look like a ramp of, what, 3,000 in October, 10,000 in November, and 26,000 in December?
which would then even if plateaued put 2024 production at 312,000 units?
I think that “reader” is … too optimistic
As context, yesterdays Q&A on the point:
- Q: once CT is fully ramped in Austin what is the target production "we'll start production and handing over cars later this year, there will be an S-curve of production, and I guess we'll see what the demand is, we're likely to do a quarter million a year, maybe more, very much dependent on what the demand is like.”
| 9/22 | 9/29 | 10/6 | 10/13 | 10/20 | 10/27 | 11/3 | 11/10 | 11/17 | 11/24 | 12/1 | 12/8 | 12/15 | 12/22 | 12/29 | 1/5 |
| 500 | 950 | 1250 | 1600 | 2000 | 2200 | 2400 | 2600 | 2800 | 3000 | 3200 | 3000 | 3250 | 3500 | 3750 | 4000 |