I just got a quote from Trout for $9,082.00 and have some questions:
- Is that price reasonable? I don't have anything yet.
- Can I get a different quote or only from Trout?
- Payment: I have to pay upfront and get reimbursed later? I believe it's only $4K right?
- If I refuse I can only get $700 to shop, correct?
200 Amp Panel
Existing panel is overloaded. Load calculation will not allow EV charger without a panel upgrade to 200 amps. Demo old panel and replace with a new 200 amp main breaker all in one. Solar ready. Includes all new breakers.
15 year warranty
2,988.00
Main Grounding System
Install main ground system to bring the current electrical system up to NEC code
998.00
Whole House Surge Protection
Due to new 2023 NEC code we will provide and install a whole house surge protector
421.00
Install a Tesla supplied Gateway
Install a Tesla supplied gateway within 5 feet of the main panel. This includes relocating the light loads from the panel within 5 feet
3,300.00
Installation of a Tesla supplied Tesla universal charger
Installation of a Tesla supplied Tesla universal charger within 10 feet of the panel. This includes the communication wiring to communicate with the gateway.
725.00
City permits and fees
Includes all permit, inspection and utility fees
650.00
Exclusions
Stucco repair. Price is valid if meter spot comes back in same location. Will require a utility meter spot which takes 7-10 business days to finish
- Is that price reasonable? I don't have anything yet.
- Can I get a different quote or only from Trout?
- Payment: I have to pay upfront and get reimbursed later? I believe it's only $4K right?
- If I refuse I can only get $700 to shop, correct?
200 Amp Panel
Existing panel is overloaded. Load calculation will not allow EV charger without a panel upgrade to 200 amps. Demo old panel and replace with a new 200 amp main breaker all in one. Solar ready. Includes all new breakers.
15 year warranty
2,988.00
Main Grounding System
Install main ground system to bring the current electrical system up to NEC code
998.00
Whole House Surge Protection
Due to new 2023 NEC code we will provide and install a whole house surge protector
421.00
Install a Tesla supplied Gateway
Install a Tesla supplied gateway within 5 feet of the main panel. This includes relocating the light loads from the panel within 5 feet
3,300.00
Installation of a Tesla supplied Tesla universal charger
Installation of a Tesla supplied Tesla universal charger within 10 feet of the panel. This includes the communication wiring to communicate with the gateway.
725.00
City permits and fees
Includes all permit, inspection and utility fees
650.00
Exclusions
Stucco repair. Price is valid if meter spot comes back in same location. Will require a utility meter spot which takes 7-10 business days to finish
| Total | $9,082.00 |