From reading through different people's quotes, there are at least 3 different procedures being quoted.
Main Breaker Separation - Main panel becomes sub-panel of gateway.
Light Loads Backup - Gateway is sub-panel of main panel, up to 10 light circuits moved to gateway.
Heavy Loads Backup - Gateway is sub-panel of main panel, mix of light and heavy circuits moved to gateway.
The 2 load backup options are going to be considerably more labor and material intensive, each is going to require splicing new wiring in the existing panel over to new breakers in the gateway. Moving 10 circuits is probably adding $1,500 to any quote, assuming only minor gouging.
Main Breaker Separation - Main panel becomes sub-panel of gateway.
Light Loads Backup - Gateway is sub-panel of main panel, up to 10 light circuits moved to gateway.
Heavy Loads Backup - Gateway is sub-panel of main panel, mix of light and heavy circuits moved to gateway.
The 2 load backup options are going to be considerably more labor and material intensive, each is going to require splicing new wiring in the existing panel over to new breakers in the gateway. Moving 10 circuits is probably adding $1,500 to any quote, assuming only minor gouging.